Malin Head Offshore Wind Farm

projects

Source Galileo is currently investigating the feasibility of developing the Malin Head Offshore Wind Farm. The proposed project area is located off the coast of County Donegal, 32 km north of Malin Head. The area has been selected far offshore in order to reduce potential visual and environmental impacts whilst enabling stronger wind resources to be harnessed.

Malin Head Offshore Wind Farm

As the project is aligned with national renewable energy and climate mitigation policies, it has the potential to help Ireland meet national, European and international commitments whilst also
supporting local supply chain, employment opportunities and community benefits.

Bird and marine mammal surveys commenced in September 2021 and Source Galileo are planning further site investigations in order to better understand the environmental and physical characteristics of the 275sqkm offshore area.

The outputs from these studies will inform the design of the wind farm which has a potential capacity of over 1,000 MW (1 GW) of renewable energy, enough to power over 1 million homes while also helping to address the climate and energy security crisis.

The process of proactive public consultation, engagement and communication with the local
community, statutory consultees and interested parties will underpin and inform Source Galileo’s approach to developing the Malin Head Offshore Windfarm.

Malin Head – Indicative Project Timeline

From this early stage through to a prospective operations phase and production of renewable energy, the proposed project is expected to follow the indicative timeline below.

2021

Appoint Fishery Liaison Officer and commence environmental surveys

2022

Stakeholder engagement and ongoing environmental surveys

2023

Maritime Area Consent (MAC) application, public consultation and engagement

2024

Grant of Maritime Area Consent (MAC), public consultation and engagement

2025

Pre-application consultation ahead of submission of planning application to An Bord Pleanála

2026

Planning application to An Bord Pleanála, public consultation and engagement

2027

Planning permission granted by An Bord Pleanála

2028

Commence construction, public consultation and engagement

2029

Offtake connection

2030

First energy generated, continued public consultation and engagement

Note: timelines may change due to external factors outside the control of Source Galileo.

Have Questions? Please get in touch